Gentlemen

I have the honor to submit the following estimate of work done for the quarter ending March 31st 1878. 

22600 Yds of Earth @ 20 c $1520
14300 Yds of Rock @ 1.00 14300
900 Yds of Tunnel @ 11.00 3600

Total $22420

Respectfully submitted

Jas. W. Wilson